Crews opened four lanes on the bridge to traffic Monday night -- two westbound lanes, one eastbound lane and one eastbound left turn lane. There is still some work around the bridge to complete the sidewalk work and the last two lanes. That should continue through about mid-October. We were originally scheduled to have lanes open to traffic in early September, but some utility issues and the major flooding through the area delayed that anticipated opening. We will be adjusting some of the pavement on Hanley to meet the updated grades through the course of the project. Andrew Gates, MoDOT Communications
We do have a lot of maintenance work scheduled to happen over this weekend during the full interstate closure, including some of the tasks that you mention. Andrew Gates, MoDOT Communications
I-44 is set to close between Friday night at 7 p.m. and Monday morning at 5 a.m. I have asked our construction team to check the board on I-44 at Jefferson to make sure that the date is correct. Andrew Gates, MoDOT Communications
MoDOT maintains Route 366 in the county and oversees the driving surface in the city on Chippewa. We've passed your observations along to the appropriate teams to check out. Andrew Gates, MoDOT Communications
We are still projecting that to open in mid-October. Andrew Gates, MoDOT Communications
Thanks -- I have shared your observation with our maintenance team. Andrew Gates, MoDOT Communications