2 questions:
1) we & many commuters use S Jefferson between Chouteau & Lafayette to access I 44… and it is full of large, unavoidable, potholes. Is some sort of repair planned soon for this stretch of road?
2). We frequently walk between Chouteau and Market…to the PO etc, and find the blockage on 18th St. In front of Ameren makes this difficult. We have also noticed that it creates a blockage for drivers exiting the city going S on Truman Parkway. When will that blocked lane be reopened? -
Thank you for your concerns. (1) Street Maintenance crews are in the process of repairing potholes on Jefferson from St Louis Ave to Gravois. Paving is scheduled for Jefferson from Chouteau to Gravois in near future. (2) I'll reach out to Ameren to receive an update timeline for completion of project...Larry Tyler / Street & Traffic Liaison
-
-
Right now, we have a project scheduled for that area in 2023. We'll have to do some sidewalk updates along the corridor first, so I wouldn't expect resurfacing until maybe early 2025. If you have specific areas where there are potholes, or very rough pavement, you can share them with our customer service team 24/7 at (314) 275-1500 or 1-888-ASK-MODOT, and our maintenance team can take a look and see what may be able to be done. Andrew Gates, MoDOT Communications
-
-
-
-
-
-